Construction Update: the Foundation Phase

3 hours ago
2 min read

Big milestones are happening on site! Crews have officially wrapped up excavation and moved into the foundation phase of the Lac-Brome Museum expansion.


Here is a quick look at our progress and what to expect when you visit.


What’s Happening on Site?


  • Excavation Complete: Crews successfully cleared a massive layer of bedrock where our new basement will sit. To protect our historic buildings without using explosives, the team used a robotic drill and a specialized rock splitter to break the stone foot by foot.

  • Current Work – Pouring Foundations: Foundation footings are in place. Over the next few weeks, crews will pour concrete into the forms, aiming to finish the foundations before the holiday break.

  • Looking Ahead to 2027: Wall panels and roof beams go up this winter to complete the building shell by spring. We remain on track to finish construction in Fall 2027, with new exhibits opening a few months later.


What to Expect When You Visit


The Museum remains OPEN! Our temporary exhibition and Children's Museum remain accessible to visitors unless announced otherwise. Since we are in the winter season, our exhibition buildings and pavilions are closed until the spring.


Here are a few quick practical details:

  • Site Hours & Noise: Construction runs Monday to Friday, from 7:00 a.m. to 5:00 p.m., though the loudest rock-splitting phase is now behind us.

  • Parking: The parking lot between the Museum and Town Hall remains closed to the public and reserved for construction.

  • Roads: Expect a steady lineup of cement mixer trucks along Lakeside Road and St. Paul over the next few weeks during concrete pours. Please use extra caution near the site.